Specification of the BCM Core-Facility-Management-System

10/28/2015 03:37 PM

The document describes the functionality of the BCM Core-Facility-Management-System.

01 - Cahier des charges

03/21/2016 10:32 AM

02 - Les conditions d’acceptation du projet

03/21/2016 10:35 AM

03 - La planification du projet en étapes

03/21/2016 10:39 AM

*Milestones: *

  • CFMS Administration
  • Development until 31.08.17
  • Paused from 01.09.2017 to 01.06.2018
  • Validation until 31.12.2018
  • Alpha-tests from 01.01.2019 to 28.02.2019
  • Beta-test from 01.03.2019 to 01.04.2019
  • Production from 01-05-2019

...

04 - Les attributions des responsabilités

03/21/2016 10:39 AM

Development:
Eric Lanave (developer mri)
Volker Baecker (responsible mri-software)

Test:
Myriam Boyer Clavel (staff mri)
Sylvain de Rossi (staff mri)
Matthieu Richard (staff bcm billing)
Julio Mateos Langerak (staff mri)
...

05 - La description des outils techniques

03/21/2016 10:40 AM

IDE:

eclipse

Continuous Integration Server:

jenkins

Source Code Repository:

git

Development Server Environment

docker

06 - Les conditions de stockage de donnes

03/21/2016 10:40 AM

All data is hosted internally by the IT service of MRI. The source code of the project will be made available in a public github repository.

Development:
The code is divided into the programs that run on the two different servers and the code that runs on the clients.
...

07 - Les exigences légales

03/21/2016 10:41 AM

User data acquired by the software is subject to a declaration at the CNIL (number 1084525). Unused data must be deleted after 5 years.

The project will be distributed as an open source project under the CeCILL-B license.

08 - Les informations issues de conceptions similaires

03/21/2016 10:41 AM

Z. Cseresnyes, A. Sporbert, F.Kriegel, Core Facility Management, Imaging & Microscopy, Nov. 28, 2011

- online registration and user database with webinterface
- helpdesk: osTicket
- communication: DokuWiki, mailing lists
- booking: Google calendar...

09 - Les exigences spécifiques

03/21/2016 10:42 AM

The facility is distributed at different places using different IT-networks. The components of the system must be able to communicate in this setup without having to asks the opening of specific communication ports.

10 - La définition des voies de valorisation prévus

03/21/2016 10:42 AM

The project has been presented as a poster at the "Assises des PF" of the network "RTMFM - Microscopie Photonique de Fluorescence Multidimensionnelle" in 2016 at Montpellier.

The project is an open source project that is available to the scientific community. The source code will be made available under the CeCILL-B license on GitHub.
...

Technical documentation

project description

06/27/2015 10:01 PM

A short introductory description of the Core-Facility Management System Project